Abstract:Presents the HVAC system and its control logic used in the Maintenance Hot Workshop.Commission the HVAC system,finds that the exhaust air flow rate in some rooms is insufficient,the temperature inside cannot meet the design requirement. Analyse the causes.According to the analysis, summarizes the factors which should mainly be considered when design,commissioning,operating, maintaining the system. Emphasize the importance of system commissioning on the normal operation of HVAC system in Maintenance Hot Workshop.
标题:某核电厂热检修厂房暖通系统调试研究与分析
title:Research and Analysis of HVAC System Commissioning in Maintenance Hot Workshop
作者:刘世昊, 罗伟涛
authors:LIU Shi-hao, LUO Wei-tao
关键词:热检修厂房,空调通风,调试,
keywords:maintenance hot workshop,air conditioning and ventilation,commissioning,